A zinc production furnace of the type above generates a vapor analyzing 47% metallic
zinc, 53% carbon monoxide. The vapor is quenched to generate three metric tons
of metallic zinc per hour. The volume of gas generated (cubic meters) by the furnace
per hour at 950°C and 1.2 atm absolute pressure is most nearly:
|
(A)
|
2,189
|
|
(B)
|
3,838
|
|
(C)
|
6,343
|
|
(D)
|
8,167
|